We have been working on
building a new facility for several years and a few years ago entered into a
construction loan agreement with Harris Bank. When we entered into the
agreement they were unwilling to loan us enough money to finish the project,
our banker indicated they preferred to loan us a little to get started with
and promised to add funds as the church grew and the project moved along.
In
March of 2008 we held a fundraiser and received pledges totaling
about $500,000 over a three year period. This information was submitted to
our banker and we were told that the bank would lend us another $900,000
toward our new facility. We were even told we could write a check knowing it
was going to over draw our account, but were told by the bank they would
honor it because the additional money for our loan was about to come
through.
The $900,000 would have
been enough in our opinion to have finished phase one of the project. Phase
one would include construction of the entire outer shell of the building,
finishing the two gymnasiums and the classrooms for our school and Sunday
School. We would worship in one of the gyms while the money was raised to
complete the sanctuary.
As time drug on into
the later spring and early summer of 2008 the communication with the bank
became more and more difficult to complete. We were finally told that our
banker had left, we later learned he had been dismissed.
During the summer (June
or July), the bank requested a meeting with our Pastor, our Finance Team and
Trustees. In this meeting the bank informed us that the construction efforts
were not completed to code, that the bank had commissioned a review of the
project to date. The review had revealed that the steel hadn’t been erected
properly, that the concrete was not to code and no inspections had been
completed.
We refuted all of the
banks claims, the construction had been inspected by the Village of
Channahon, concrete was not allowed to be poured at any time without a
village inspector approving first. The village had inspected and approved
all of the steel work and all of the septic system had been inspected and
approved by the health department.
During this same
meeting the bank informed us that the work that had been done would have to
be torn down, scrapped and started over from the start. They estimated the
total to complete the project at more than 11 million dollars.
All of our estimates
had put total construction of the entire facility at just under 6 million
dollars. The bank would not show us their report, they told us we would have
to pay them 6 thousand dollars to get a copy. We still have not seen the
report the bank referred to in this meeting.
During this meeting the
bank also floated out the idea that they would possibly begin foreclosure
proceedings on the property. This meeting, and the statements made by the
bank, caused a lot of concern and fear in the church. Many people left for
fear that the bank was going to foreclose on our property.
Sometime later in the
fall of 2008, we received a letter from the bank indicating that we had
until October 18 to pay off the entire loan amount. Presently that loan
amount sits at just under 1.5 million dollars.
We have received two
other similar letters which have extended the date for payment of the loan.
We receive monthly statements indicating the loan is past due. Recent
statements from the bank have indicated that foreclosure proceedings may be
much closer to starting than they have in the past. While the bank has not
explicitly said it, they have made stronger statements to our attorney to
this effect.
Throughout the entire time, FBC has continued to make the monthly payments
on the loan. To date, we have not missed a single payment and to my
knowledge we have not been late on any payments either.
In March of 2009 we did
receive a letter from Harris Bank indicating their intentions to move
forward with a foreclosure. While there was some concern in the church, the
church went to its knees and prayed for God's deliverance believing that an
answer was near.